Project Description & Goals:

The West Spring Creek Downstream of E Phillips Ave is a Channel Stabilization project located within the Foxridge neighborhood.  The goals are to create a more stable and resilient channel that meets the needs of the residents, SEMSWA, SSPRD, and project stakeholders.

The Project will address deteriorating retaining walls, channel instability, and improve maintenance, access, safety, and ecological function. 

 

Project Location:

Project Timeline:

The image outlines a project timeline: Planning (Fall 2023), Design & Permitting (Spring 2024 - Fall 2026), Construction (Winter - Summer 2027), and Revegetation (Fall 2027).