Project Name
|
Description
|
Schedule
|
|
|
Piney Creek Phase II - Upstream of Caley Ave
|
Stream stabilization design and construction
|
Winter 2013
|
|
|
Jewell Avenue Culvert Replacement
|
Culvert replacement
|
|
|
|
Lincoln Executive Center East Pond
|
Regional Water Quality facility
|
Winter 2012
|
|
|
Littles Creek Ponds
|
Pond modification
|
Fall 2013
|
|
|
Lone Tree Creek, Pond L1 West
|
Regional stormwater pond design and construction
|
Underway
|
|
|
Caley East Pond
|
Regional stormwater pond design and construction
|
Underway
|
|
|
Lone Treek Creek, Pond L2
|
Regional stormwater pond design and construction
|
Winter 2012
|
|
|
Little Dry Creek Reach 6
|
Stream stabilization design and construction
|
Fall 2012
|
|
|
Willow Creek Quebec to Dry Creek Stream Stabilization
|
Stream stabilization design and construction
|
Fall 2012
|
|
|
Windmill Creek Pond W1
|
Regional stormwater pond design and construction
|
Winter 2012
|
|
|
Big Dry Creek Tributary B @ Forest Park
|
Tributary B stream stabilization design and construction
|
Winter 2012
|
|
|
First Creek Culvert @ Jewell Ave
|
Roadway culvert replacement design and construction
|
Sprint 2012
|
|
|
Tallgrass Sediment Pond Removal
|
Sediment pond removal and grading
|
Winter 2012
|
|
|
Dove Creek Pond D2
|
Regional stormwater pond design and construction
|
Underway
|
|
|
Cherry Creek @ Eco Park
|
Stream stabilization design and construction
|
Fall 2012
|
|
|
Piney Creek at Tower Rd
|
Sediment pond and channel stabilization
|
Fall 2013
|
|
|
Cherry Creek drop structure @ 17 Mile House
|
Stream stabilization design and construction |
Underway
|
|
|
East Toll Gate Creek Pond @ Gun Club Rd
|
Regional stormwater pond design
|
NA
|
|
|
Goldsmith Gulch at Peakview Ave
|
Stream stabilization design and construction
|
Fall 2013
|
|
|
Cherry Creek at Arapahoe Rd - Phase I
|
Stream stabilization design and construction
|
Fall 2013
|
|